"We are not talking of repairing it. We are talking of replacing it."
Tampa's chief deputy financial officer, Mike Perry, said that to City Council on February 5, 2026, according to the meeting transcript published by Tampa Meetings. Council member Bill Carlson had just asked how long it would take to repair the Ballast Point Pier.
Five months earlier, the City had announced the opposite. A September 2025 release, titled "Project To Restore Ballast Point Pier Has Begun," said engineering reports showed the 100-year-old pier "can be restored rather than be rebuilt from scratch," and that this "will cut years off the wait." In its own words, Mayor Jane Castor's office calls Ballast Point Park "a popular spot to start walks and bicycle rides along Bayshore Boulevard." That puts the pier at the south end of the same waterfront Bayshore Beautiful looks out on.
The pier's return now runs on federal review, and the City's newest paperwork starts the design over. For the next several years, the south end of Bayshore means the park without its pier.
Four documents, and how the plan changed
The City's own records show the plan shifting over roughly a year.
| Date | Document | What it said about the pier |
|---|---|---|
| Sept. 4, 2025 | City news release | It could be restored; reinforced pilings, new boards, upgraded plumbing, lighting and electrical; no completion date |
| Sept. 25, 2025 | RFQ 26-C-00002, "Ballast Point Public Pier Replacement Design-Build" | One team to design and build it, estimated at $14 million to $17 million |
| Feb. 5, 2026 | City Council meeting | A design-build firm had been shortlisted; FEMA review would slow everything down; "three to four years" |
| Sept. 4, 2026 | RFQ 26-D-00002, "Ballast Point Public Pier Replacement Design" | Hire an engineer to design "a new public pier," for a fee of $1.4 million to $1.7 million |
The two price ranges cover different jobs. The 2025 estimate covered a design-build contract, meaning one team handles both drawing and building. The 2026 figure is only the engineers' fee. Tampa Bay Business & Wealth reported that the new solicitation gives no construction budget and no completion date. The firm that wins it will write the construction estimate.
The DemandStar bid record for the earlier design-build solicitation lists it as "Under Evaluation." The new one covers design only. The scope includes "Structural assessment of existing pier and feasibility analysis for repairing existing pier structure," then design, permitting, bid documents, construction oversight and public outreach. Submissions to the City's RFQ were due before 2 p.m. on October 8, 2026.
Why FEMA sets the pace
Perry told Council the City asked FEMA for a replacement on September 26 and heard nothing back until two days before the February meeting. He added that FEMA had changed its local management in January and "seemed to be much more responsive."
The size of the project is what slows it down. Perry explained that FEMA classifies anything costing more than $1 million as a "major project," so the agency "will be reviewing every step," including "how we select the design bid firm or the architects and everything else." When Council Chair Lynn Hurtak asked why the September release never mentioned FEMA, Perry said the pier "was always a project destined to be funded by FEMA."
Hurtak said the release's "restore" headline gave "people the impression it is coming soon." Carlson said it was "better to tell people what it might be and then if it ends up being shorter, that is better."
What the remaining steps add up to
Perry's estimate was a design phase of "a year to 18 months" and "maybe up to two years to construct," followed by "Don't hold me to that. I am not a pier engineer." Here is what still has to happen, in order, under the September 2026 solicitation:
- The City selects an engineering firm from the October 8 submissions.
- The firm assesses what remains of the old pier and whether any of it can be repaired.
- The firm designs the replacement, which Perry estimated at 12 to 18 months.
- The project needs permits from the Florida Department of Environmental Protection and the U.S. Army Corps of Engineers.
- The construction contract goes out to bid.
- Construction takes up to two years, by Perry's estimate.
Apply Perry's own numbers to that sequence. Suppose a design contract started early in 2027. Eighteen months of design runs to mid-2028, and two years of construction after that reaches 2030. Counting his three-to-four-year estimate from the February 2026 meeting lands in 2029 or 2030. Neither date is a City target, and the permitting and bidding steps between design and construction aren't in his estimate at all.
What the new pier is designed to be
The replacement would generally follow the former pier's dimensions, with final measurements set by a field survey. Tampa Bay Business & Wealth summarized the specs: about 940 feet long and 12 feet wide, a 28-by-42-foot pier head, and a copy of the 14-by-25-foot gazebo that stood at the end.
The materials are built for storms. The preliminary specs call for 5,000-psi marine-grade concrete piles about 13 feet apart, treated Southern Pine framing, 316 stainless-steel connections and composite decking that resists slipping, UV, rot and termites. The preferred gazebo roof is standing-seam aluminum rated for winds of at least 145 mph. The plans also include marine-rated LED lighting, rescue ladders, fishing signage and conduits for future power or water. While the piles go in, the work requires seagrass protections and floating turbidity curtains.
Built this way, the pier would continue a long history. The original was destroyed in the 1921 Tarpon Springs hurricane, rebuilt, and reopened in April 1925. It stood until Helene and Milton in 2024. The City says the finished pier will be open 24 hours a day, seven days a week, as before.
January's exception
The solicitation notes one job the pier does besides fishing and walking. It "is also used as a loading point for the Jose Gaspar vessel during the Gasparilla parade events."
To keep that possible during the closure, Council approved a license with Ye Mystic Krewe of Gasparilla covering the 2026 through 2028 events. It allows a temporary retrofit with replacement planks, temporary aluminum gangways and railings so krewe members can board and get off at Ballast Point. The retrofit is for the krewe and the event. It does not reopen the pier to the public.
The weather overruled it last season. WUSF reported that conditions sent the ship straight from Port Tampa Bay to the Tampa Convention Center. The official Gasparilla site lists the 2027 Pirate Fest for January 30 and the Outbound Voyage for February 27.
The park at the end of Bayshore, meanwhile
The rest of Ballast Point Park is open on its normal schedule, according to the City's park page:
- Park hours run 6 a.m. to 8 p.m.
- Splash pad hours are 8 a.m. to 4 p.m., with benches around it.
- Playground: semi-shaded, with slides, bridges and a Tot Lot for younger kids.
- Leon's Lobstah Shack serves New England-style seafood and ice cream, Tuesday through Sunday, 11 a.m. to 8 p.m. It's closed Mondays. The listed number for the restaurant and bait shop is (813) 831-2112.
- Boat ramp: single lane, open 24 hours, with only four trailer parking spots.
- Boat dock: cleats for free temporary docking, just north of the closed pier.
- Octagonal gazebo and shelters near the playground can be reserved through the City, and some shelters are first-come, first-served.
Fishing from a structure in South Tampa is harder right now. Carlson asked at the February meeting where people south of Gandy should go instead. Parks official Ted Fowler named the pier at DeSoto Park, Palmetto Beach, the fishing piers at Al Lopez Park, and Williams Park. Carlson admitted those weren't "ten minutes away but within 30 minutes."
Picnic Island, the other South Tampa pier, has its own problem. WTSP reported that a section of that pier fell between two pylons on a Saturday night while it was still open. The City is planning a shoreline restoration there with living breakwaters, dunes and oyster habitat. Tampa Bay Business & Wealth reported that the City was seeking a $1.999 million design agreement with HDR Engineering for that work, and the scope does not include the pier.
For anyone walking or biking from Bayshore Beautiful to the south end of the boulevard, the trip still ends at Ballast Point Park. The playground, splash pad, shack and boat ramp are open. The pier is the part still waiting on a design contract.
At 1 Step Ahead Realty Group, we follow South Tampa projects like this one because they shape everyday life in the neighborhood. If you'd like help understanding how the waterfront plans around Bayshore and Ballast Point might matter for your home, reach out to Raquel and the team. Get Started Today.